Review Agenda Item
Meeting Date: 8/25/2022 - 6:00 PM
Category: Purchasing
Type: Action
Subject: 9.32 Change Order One to Repair of Damaged Exterior Wall at Lincoln School Contract 9430
Strategic Plans:
Priority 1.5
1.5 Develop a capital strategy aligned with the Long-Range Facilities Plan and strategic plan to modernize all facilities, and plan for enrollment projections, academic programs, and community needs.
Enclosure
File Attachment:
Summary: WHEREAS, in response to the COVID-19 National Declaration of Emergency bids were electronically received on Thursday, November 4, 2021 after public advertisement for Repair of Damaged Exterior Wall at Lincoln School, request for bids were issued to twenty (20) vendors with two (2) vendors responding; and

WHEREAS, the Newark Board of Education awarded a contract to Spartan Construction, Inc., 399 Oak St., Suite C, South Amboy, NJ 08879 at the May 26, 2022 Board Meeting in the amount of $122,000.00 with a requested 20% contingency allowance in the amount of $24,400.00; and

WHEREAS, change order one addresses additional repairs to the west elevation of the school intended to address a series of holes through the brick which can be a likely source of water infiltration; and

WHEREAS, the cost of change order one is four thousand eight hundred twenty-four dollars ($4,824.00); and

WHEREAS, change order one was reviewed and approved by Carlos Edmundo, Interim Executive Director of Facilities Management and Krystle Whitlock, Assistant School Business Administrator.
Funding : Subject to availability of funds.
30-30-000-401-450-351-190-000
Recommendation to the Board: NOW, THEREFORE IT IS HEREBY RESOLVED, that the Newark Board of Education accepts and approves change order one in the amount of $4,824.00 increasing the contract value to $126,824.00. Remaining contingency will be $19,576.00.

Explanation: Additional repairs to damaged exterior wall at Lincoln School.
Approvals:
Recommended By:
Signed By:
Nicole Yarbough - Purchasing Manager
Signed By:
Joao Dias - Budget Officer
Signed By:
Krystle Whitlock - Assistant Business Administrator
Signed By:
Sherelle Spriggs - Senior Purchasing Manager
Signed By:
Valerie Wilson - School Business Administrator
Signed By:
Roger León - Superintendent
Vote Results:

Original Motion
Member Josephine Garcia Moved, Member Daniel Gonzalez seconded to approve the Original motion 'NOW, THEREFORE IT IS HEREBY RESOLVED, that the Newark Board of Education accepts and approves change order one in the amount of $4,824.00 increasing the contract value to $126,824.00. Remaining contingency will be $19,576.00.

Explanation: Additional repairs to damaged exterior wall at Lincoln School.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 8 Nay: 0.
The motion Carried 8 - 0
   
Josephine Garcia     Yes
Flohisha Johnson     Yes
Dawn Haynes     Yes
Asia J. Norton     Yes
A'Dorian Murray-Thomas     Yes
Vereliz Santana     Yes
Daniel Gonzalez     Yes
Crystal Williams     Yes